How to Use This
Book
This manual is a guide to the cost of installing electrical work
in buildings. It lists costs to the electrical subcontractor for a
wide variety of electrical work.
Before using any estimate in this book, you should understand an
important point about estimating electrical construction costs.
Estimating is an art, not a science. There is no estimate that fits
all work. The manhour estimates in this book will be accurate for
many jobs. But no two crews will complete all tasks in exactly the
same time. And no two jobs are identical. That’s why electrical cost
estimating requires an exercise of judgment. Every estimate has to
be custom-made for the job, the crew and the contractor. No
estimating reference, no computerized cost estimating system, no
estimating service can consider all the variables that make every
job unique.
This book is not intended as a replacement for well-informed
judgment. But when supplemented with an estimator’s professional
evaluation, the figures in this manual will be a good aid in
developing an informed opinion of the cost of electrical systems.
Inside
the back cover of this book you’ll find an envelope with a compact
disk. The disk has National Estimator, an easy-to-use estimating
program with all the cost estimates in this book. Insert the CD in
your computer and wait a few seconds. Installation should begin
automatically. (If not, click Start, Settings, Control Panel,
double-click Add/Remove programs and Install.) Select Show Me from
the installation menu and Julie will show you how to use National
Estimator. When Show Me is complete, select Install Program. When
the National Estimator program has been installed, click Help on the
menu bar, click Contents, click Print all Topics, click File and
click Print Topic to print a 28-page instruction manual for National
Estimator.
Labor Costs
The labor costs listed in this manual will apply on most jobs
where the hourly wage in effect is the same or similar to the
following rates:
Journeyman Electrician Base Wage, $27.25 per hr.
Taxable Fringe Benefits at 5.15%, $1.40 per hr.
Taxes & Insurance at 20.04%, $5.74 per hr.
Non-taxable Fringe Benefits at 4.55%, $1.24 per hr.
Total Labor Cost, $35.63 per hr.
The total hourly cost includes the basic wage, taxable fringe
benefits (vacation pay), workers' compensation insurance, liability
insurance, taxes (state and federal unemployment, Social Security
and Medicare), and typical nontaxable fringe benefits such as
medical insurance.
If your hourly labor cost is much lower or higher, costs of
installation can be expected to be proportionately lower or higher
than the installation costs listed in this book. If your total
hourly labor cost is 25 percent less, for example, reduce the labor
figures in the cost tables by 25 percent to find your local cost.
The Craft@Hrs column shows the recommended crew and manhours per
unit for installation. For example, L2 in the Craft@Hrs column means
that we recommend a crew of two electricians. L 1 means that a crew
of one electrician is recommended. Costs in the Labor Cost column
are the result of multiplying the manhours per unit by the rate of
$35.63 per hour.
For example, if the Craft@Hrs column shows L2@.250, the Labor Cost
column will show $8.91. That's .250 manhours multiplied by $35.63
per manhour and rounded to the nearest penny.
Divide the manhours per unit into 8 to find the number of units one
electrician can install in one 8-hour day: 8 divided by .250 equals
32 units per day. Multiply that amount by the number of crew members
to find the number of units the crew is likely to install in an
8-hour day. For example, if the crew is two electricians, multiply
32 by 2 to find that the crew can be expected to install 64 units in
an 8-hour day.
Some tasks require less labor under certain conditions. For example,
when conduit is run in groups, less labor is required for each 100
linear feet. It's the estimator's responsibility to identify
conditions likely to require more or less labor than the standard
for the type of work being estimated.
This book lists both the labor cost per installed unit and the
manhours required for installation. Manhours are listed in
hundredths of an hour rather than minutes, making it easier to
calculate units.
Material Costs
Material prices in this book are based on costs as of late 2006,
and projected to mid 2008 by adding 3 to 8
percent. Prices are neither “retail” nor “wholesale” costs. Instead,
they’re intended to reflect what most electrical contractors who buy
in moderate volume will be paying in spring 2008.
Volume purchases of some materials will cost less because many
dealers offer quantity discounts.
Material costs in this book include normal waste. If waste of
materials or breakage is expected to exceed to 5 percent of the
materials used on the job, include a separate allowance for
excessive waste.
The cost of delivering materials to the job site is not included
in this book. Where the cost of delivery is significant and can be
identified, add that cost to these figures.
Please note that the cost of some electrical materials is highly
volatile. For example, copper wire prices have been known to move up
or down 10 percent in one month. There’s no reliable way to forecast
price movements like this. Major price changes have not been assumed
in this manual.
Add Sales Tax
No state or local sales tax is included in material prices listed
here. Sales tax varies from area to area and may not be charged on
purchases for some types of projects. Add the appropriate sales tax
rate when sales tax will be charged on materials bought for the job.
Add Overhead and Profit
To complete the estimate, add your overhead and expected profit.
Many contractors feel that adding 10 percent for profit yields an
acceptable return on the money invested in the business. But there’s
no profit percentage that fits all jobs and all contractors.
For some electrical contractors, overhead may add as little as 10
percent to the labor and material cost. But routinely adding 10
percent for overhead is poor estimating practice. It’s the
estimator’s responsibility to identify all overhead costs and
include them in the estimate, either as a lump sum or as a
percentage of the total labor and material cost.
Other Costs to Add
Some other costs are excluded from the figures in this manual:
building electrical permits, special hoisting costs, freight costs
not absorbed by the supplier, utility company charges for
installation and service, special insurance and bonds, power
equipment other than small tools, mobilization to remote sites,
demobilization, nonproductive labor, and nonworking supervisors. Add
these costs if they can be identified and if they will be a
significant part of the job cost.
All Tables Assume “Good” Conditions
This means that there are few or no unusual conditions that would
delay production. Conditions are good when work is performed during
usual working hours in relatively clean surroundings and in readily
accessible areas not over 12 feet above the finish floor. The
temperature is between 50 and 85 degrees F. Electricians are working
no more than eight hours a day and no more than five days a week.
Good conditions require that all tools and materials be available
on the job site when needed. Tools, including power tools, are
assumed to be in good working order. Where power tools are
appropriate, it’s assumed that temporary power is provided. Add the
cost of temporary power when it will be furnished at your expense.
Proper supervision can make a big difference in labor
productivity. The tables assume that there is adequate supervision
but make no allowance for nonproductive labor — supervisors who
direct but do no installation. If you plan to have nonproductive
supervision on the job, add that cost to the figures in this manual.
Conditions are seldom “good” when the work area is confined or
when a short construction schedule makes it necessary for many
trades to work at the same time. The usual result will be stacks of
material obstructing the work space and several tradesmen competing
for access at the point of installation.
If the conditions on the job you’re estimating aren’t expected to
be “good,” adjust the labor figures in this book as appropriate.
Occasionally larger jobs can be done faster because specialized
equipment or specialized crews can be used to good advantage. This
will usually reduce the installation cost. More often, conditions
are less than “good.” In that case, labor costs will be higher.
There’s no accepted way to decide how much “bad” conditions will
increase the labor hours needed. But it’s accepted estimating
practice to assign a cost multiplier of more than 1.0 to a job that
can be expected to require more than the usual amount of labor per
unit installed. For example, if conditions are less than “good” only
in minor respects, you might multiply labor costs by 1.10. If
conditions are very poor, a multiplier of 1.50 or more might be
appropriate.
Other Factors That Affect Productivity
The tables in this book assume that the crew used for the job is
the smallest crew appropriate for the work at hand. Usually this
means that the crew is one journeyman electrician.
Most experts who have studied the productivity of construction
trades will agree that the smallest crew that can do the job is
usually the most efficient. For example, it would be foolish to have
two men working together setting duplex receptacles — one handing
tools and material to the other as needed. Only one of the two would
be working at any given time. A more productive arrangement would be
two one-man crews, each working independently.
Of course, there are exceptions. Sometimes a crew of one will
take more than twice as long as a crew of two. When pulling feeder
cable or setting floor-standing switchboards or motor control
centers, more help will usually cut the labor cost per installed
unit. Some jobs simply can’t be done by a crew of one.
When work is done on a scaffold, there should be someone on the
ground to chase parts and equipment and prepare lighting fixtures
for hanging. It’s a waste of manpower to have an electrician leave
the scaffold and return every time parts or tools are needed. The
scaffold installers should install one fixture while the “grunt” on
the floor prepares the next. Conduit should be prefabricated on the
ground from measurements taken by the electricians on the scaffold.
The assistant on the ground should bend the conduit and hand it up
to the installers.
Labor savings like this are obvious to anyone who has ever done
this type of work, and are assumed in the labor tables in this book.
The Electrician
The labor hours in this book are intended to be typical of what a
trained and motivated journeyman electrician with five years of
experience will do on most jobs. Of course, it’s assumed that the
installer can read and follow plans and specifications and has the
ability to lay out the work so that it complies with the code.
It shouldn’t make any difference whether the work is in a
hospital, a grocery store, a wood mill or a small convenience store.
An experienced journeyman electrician should be able to handle the
work at the rates shown here even though the materials and code
requirements differ. But you’ll have to make allowances if your
installers are familiar with residential work only, and the job at
hand is something else.
Improving
Estimating Accuracy & Profit
It’s been said that electrical estimators learn by making
mistakes. The best estimators are the ones that have made the most
mistakes. Once you’ve made every mistake possible, you’re a real
expert.
I can’t subscribe 100 percent to that theory, but I know that
there are plenty of pitfalls ready to trap unwary electrical
estimators. This section is intended to suggest ways to spot
potential problems before they become a major loss. It will also
recommend some steps you can take to increase the profit on most
jobs.
Labor Productivity
Improving output only slightly can result in major cost savings.
Cutting only a minute or two off the installation time for each
duplex receptacle or handy box can reduce the labor cost by several
hundred or even a thousand dollars a job. Getting better (and
predictably better) productivity from your electricians should be a
primary concern for every electrical contractor.
Assuming that your electricians are experienced, well-trained,
and have all the tools and materials they need to complete the work,
the most significant increase in productivity will probably be
through improved motivation.
The best form of motivation for most electricians is to encourage
a sense of pride in the work they do. Encouraging self-respect is a
powerful inducement for most skilled tradesmen. Every alert
supervisor knows the value of recognition given for a job well done.
Acknowledging good work builds confidence and encourages additional
effort in the future.
Handling Inspections
The supervisor or foreman on site should have primary
responsibility for dealing with all inspectors. Don’t let others
circumvent the supervisor’s or foreman’s position.
An inspector’s only job is to see that the installation complies
with the code. They aren’t supervisors and don’t direct the work.
They can and do interpret the code and sometimes make mistakes.
Encourage the foreman or supervisor to take issue promptly with a
questionable interpretation. Ask the inspector to cite a code
reference as his authority. If the inspector insists that his
interpretation is correct, and if you feel that it’s wrong, call the
Building Official to initiate an appeal. Your trade association or
the National Electrical Contractors’ Association may be able to
present persuasive arguments in your favor.
Some inspectors have a reputation for being impossible to deal
with. Aggressive enforcement of questionable code interpretations
can severely hurt project productivity. Following the code carefully
will keep you out of most compliance problems. Every electrician and
electrical supervisor has to know the code. Code classes are taught
at night schools in many communities. Take a code class both to
understand how the code is applied and to get current on code
changes that have been enacted recently.
Mobilization and Demobilization
Many electrical subcontractors have job shacks and lockup boxes
that can be moved onto the job for storing tools and materials. Some
larger firms have trailer vans that can be moved from job to job. No
matter what type of on-site storage you use, getting set up takes
time. The bigger the job, the more time will probably be needed.
The first step is usually getting permission to set up your
storage area somewhere on site. On some job sites storage space is
at a premium. Some city projects literally have no storage space
until parts of the building are completed. Occasionally tools and
equipment will have to be stored off site. This will usually require
daily mobilization and demobilization and increase the labor cost
substantially. Be sure your estimate considers this important item.
Demobilization usually takes less time and costs less than
mobilization. Removing the surplus material, tools and equipment can
be done by helpers or material handlers rather than electricians.
One important mobilization item is temporary electrical service.
Be sure you know who pays for installation of temporary power and
who pays for power used on site during construction. It’s common for
the electrical contractor to cover the cost of electrical
distribution and service. Installation will usually be done by your
electricians and will have to pass inspection, of course.
Most communities require temporary electrical permits prior to
starting work. Before applying for the permit, contact the electric
utility and request a meeting with whoever coordinates extensions of
service — usually the planner. Before having that meeting, know what
size the service must be. The planner will let you know what voltage
is available and where the point of connection will be. Don’t end
the meeting with the planner until you’ve covered every requirement
and all procedures imposed by the electric utility.
Job Cleanup
It’s hard to get good production when trash and debris obstruct
access on the job site. That alone should be enough reason to
dispose of accumulated waste regularly. Most specifications require
that all subcontractors remove unused materials, cartons, wrappers
and discarded equipment. On many jobs the general contractor will
have the right to backcharge subs for removal of their discards if
they don’t clean the site themselves.
Encourage your crews to do their cleanup as installation is being
done. For example, each time a fixture is removed from a carton, the
tradesman should collapse the carton and throw it on the pile of
discards. It takes little more time that way and the cleanup is less
likely to be put off or ignored entirely.
Some contractors and subcontractors have a reputation for running
a dirty job. You’ve probably seen jobs that are so cluttered that
it’s hard to understand how anyone can work efficiently. As the
electrical contractor, you can’t dictate to the general contractor
or the other subcontractors, of course. But work habits of others
affect your productivity and thus your profit.
My feeling is that it’s entirely proper to discuss the matter
with the general and the other subs when accumulated debris is
slowing progress. Request a meeting right on the job in the middle
of the clutter. This alone may do the trick.
If you don’t insist on a clean job, the fire department probably
will. A dirty job site costs everyone more time and money. A clean
job is usually both more efficient and safer.
Production
No matter how simple and quick, most jobs will have some
production problems. It’s easy to explain why. Every job is unique.
Every job brings together skilled tradesmen with varying preferences
and habits. Most have never worked together before. Yet each must
coordinate the work he does with those who precede him and those who
follow. It’s normal to expect that some adjustments will be needed
before cooperation becomes routine.
Of course, the general contractor is the key to good cooperation
among the trades. A general who schedules trades properly will have
fewer problems and will help all subcontractors earn the profit
they’re hoping for. This is never automatic, of course. And some
general contractors never seem to learn how to schedule properly.
From the estimator’s perspective, it’s more expensive to work for a
contractor who has scheduling problems than it is to work for a
contractor who’s more adept at coordination. Your estimates should
reflect production problems when problems can be anticipated.
Good supervision will help avoid most production problems.
Schedule material deliveries carefully. Have the right tools on hand
when needed. Keep crews as small as possible. Don’t work your crews
more than 40 hours a week unless absolutely necessary. Too many
bodies and too many hours will erode production.
If you’re using a larger crew, don’t have everyone work together.
Instead, break the crew into two units and encourage friendly
competition between the two, with a six-pack of beer going to the
winning crew — to be consumed after hours and off the site, of
course.
Corrections
The tables in this book assume that little or no time is spent
making corrections after the work is done. Most electrical
contractors have very few callbacks.
If you’re often called back to replace faulty materials or
correct defective workmanship, one of four things is happening.
First, you could be working for some very particular contractors or
owners or handling some very sensitive work. In that case, callbacks
could be part of the job and should be included in each estimate.
Second, you could be installing substandard materials. Third, your
electricians could be doing haphazard work. Finally, your
installation procedure could be omitting fixture and circuit tests
that will locate problems before the owner finds them.
When qualified electricians install quality materials, the risk
of a callback is small. Occasionally a ballast will fail after 10 or
20 hours in use. And sometimes an owner’s negligence will damage a
circuit or switch. When this happens, accept the service work as
routine. Complete it promptly at no extra charge. Consider it cheap
advertising, a chance to establish your credentials with the owner.
You’ll probably turn the service call into some extra work later.
Your Type of Work
Most electrical contractors prefer to handle certain types of
work. Only a few have the capital, equipment and skills needed to
handle the largest jobs. Most will do residential wiring because
that’s the most plentiful work available. Some prefer private work
with as little government interference as possible. Others bid only
government jobs.
The most profitable electrical contractors specialize in one type
of work or one type of customer. The electrical construction field
is too broad to try to do everything well. Select a part of the
business that feels comfortable and concentrate on doing it as well
or better than anyone else. Of course, some of the older and larger
electrical shops will do almost any type of work. But nearly every
electrical contractor prefers some class of job over all others —
and would take only that work if there were enough available to stay
busy.
Observe the electrical contractors in your area. Notice the
companies that seem to be busiest and most profitable. See what
class of customers they service or what type of work they do most.
It’s probably easier to follow the success of another contractor
who’s found a winning formula than it is to invent a new formula
yourself.
Specialization lets you hire electricians who are specialists
too. That tends to improve productivity, keeps costs down, and
improves profits — as long as you’re handling work that’s in your
specialty.
Coordination will be easier and the profits will usually be
higher if you work for a limited number of general contractors. Some
contractors seem to be masters at putting a project together. These
same contractors probably pay promptly and treat their subs fairly.
That makes your job easier and tends to fatten your bottom line. If
you’ve found several contractors who make life more pleasant for
you, keep them supplied with competitive bids that will bring more
work into both your shop and theirs.
Most electrical contractors don’t bid government work. It’s a
specialty that requires special knowledge: complying with detailed
general conditions, observing regulations, anticipating inspection
criteria and following administrative procedures. And every branch
of federal, state and local government has its own requirements.
Those who have mastered the procedures usually do quite well when
work is plentiful. But there’s a tide of government work that rises
and falls just like the tide of construction activity in general.
Bid Shopping
Many contractors prefer projects that require subcontractor
listings. The general contractor must list the subcontractors he
plans to use, and must actually use the subs he lists. When listing
of subs isn’t required, the general can shop for lower subcontract
bids right up to the time work begins, in some cases. Even if the
general contractor has to list his subs in the contract with the
owner, the general will usually have a month or two to shop bids
after the contract is awarded.
When a general contractor uses your bid to land a job, it’s just
elementary fair play to expect that your company will get the
contract. Giving all your competition a second look at the job is in
no one’s interest but the general contractor’s. It’s a waste of time
to bid for general contractors who shop their sub bids. Neither is
it good practice to undercut another electrical contractor whose
estimate was used by the winning general contractor. Support the
effort of reputable subcontractors who promote subcontractor listing
at bid time.
Need More Help?
This book is concerned primarily with labor and material costs
for electrical construction. You’ll find only limited information
here on how to compile an estimate. If you need a detailed
explanation on how to make a material take-off and complete the bid,
another book by this author may be helpful. An order form for
Estimating Electrical Construction is bound into the last pages of
this book.
Softcover - 550 Pages
8-1/2 x 11 in.
>>
Introduction / Contents